Asset Register
|
Work Name
|
(3305009016/WC/1111530137) GP-Tilsiwa me D.A.V. school ke pass talab me nirmala ghat nirman karya |
Nature of Work |
Water Conservation
|
Work Status
|
Completed
|
Work Purpose status
|
Construction of Community Water Harvesting Ponds |
Scope of Work
|
Start Status |
End Status |
Non-existent |
Construction of Community Water Harvesting Ponds |
|
Location
|
Start Location |
Tilsiva |
Khata No. |
Plot No. |
|
|
|
Sanction No. and Sanction Date
: AS1448/21 ,
10/02/2022
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: No |
Estimated Cost (In Lakhs)
:
8.02
|
Estimated Completion Time (in Months)
|
2 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
128112 |
0 |
0 |
650046.8 |
0 |
778158.8 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
628 |
123 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
3889(7956),3890(4896),4089(11016),4090(8568),4091(6120), 4415(10608),4416(6732),4417(7956),4418(5916),4506(5916), 4850(612),4851(816),4852(408),4853(612),5419(11832), 5420(10404),5421(1632),5429(1224),5449(1224),5772(7344), 6109(9180),6110(1224),7301(5916),
|
Work start date |
26/07/2022 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|